Project History
Northstar Sharp’s has been in Foundation Drilling business for 30+ years, our management and senior operators have in excess of 80 years of experience in drilling foundations in Western Canada.
Read about our latest projects:
Eastern Alberta Transmission Line Project
Owner: | ATCO |
Location: | Eastern Alberta |
Award: | March 2013 |
Start Date: | June 2013 |
General: | Valard Construction |
The Eastern Alberta Transmission Line Project is a massive utility project spanning 488km from Gibson Alberta, to Brooks Alberta. The construction involves the installation of Concrete Pile foundations, Driven Steel Foundations and Augered grillages as well as the installation and stringing of some 1490 steel lattice transmission towers. For this project, Sharps provided drilling and installation services for Drilled pier construction, as well as machinery, engineering and manpower support for the augered grillages. Sharps designed and develop an efficient method of suspending an grillage into an open shaft and then back-filling with 20% concrete fill. This would then cure, and could be back-filled with insitu fill, allowing for enough weight to prevent structure uplift, while also providing a concrete base for the tower foundation. For drilled pier construction, Sharps deployed six drill The project also had to tackle difficult environmental conditions such as high winds (exceeding 100km/hr) as well as temperatures in excess of -40°C and +34°C. In total, close to 1000 caissons and 1280 augered grillages were installed on the EATL project totaling close to 40,000m3 of concrete. All of this was completed in just 14 months. |
Leduc Transmission Project
Owner: | AltaLink |
Location: | Leduc to Calmar, AB |
Award: | June 2012 |
Start Date: | August 2012 |
General: | Allteck Line Contractors |
Leduc Transmission, Leduc AB-28 caissons for monopole foundations |
ECTP to Sheppard Transmission Project
Owner: | Altalink |
Location: | Calgary, AB |
Award: | December 2012 |
Start Date: | February 2013 |
General: | Allteck Line Contractors |
Enmax to Sheppard Transmission-Calgary, Ab (ECPT) 15 caissons for new transmission line diameters ranging from 2440mm-3050mm and depths from 12m to 19m large diameter casings were installed and extracted with the use of a vibratory hammer on the 3050mm shafts due to poor soil conditions. |
EATL East DC Link - Brooks Project
Owner: | AltaLink |
Location: | Calgary, AB |
Award: | March 2013 |
Start Date: | May 2013 |
General: | Allteck Line Contractors |
|
500kV Transmission Line Project in NE Manitoba
Owner: | Manitoba Hydro |
Location: | Thompson to Gillam, MB |
Award: | N/A |
Start Date: | January 2016 |
General: | Valard Construction |
Over 20 personnel, 6 helical pile units, and 2 micropile units were utilized in the delivery of this project. Micropiling was utilized in areas of rock and bony tills. |
SAGD & CSS Project in Northern Alberta
Owner: | CNRL |
Location: | Cold Lake, AB |
Award: | N/A |
Start Date: | N/A |
General: | N/A |
|
500kV Transmission Line Project in Central Alberta
Owner: | ATCO |
Location: | Brooks to Fort Saskatchewan, AB |
Award: | N/A |
Start Date: | N/A |
General: | Bechtel Canada Co. |
As of Dec. of 2014, the project is approximately 100% complete. With the overall integration of Northstar into Quanta Services, and subsequently working with our sister company Valard, the successful completion of the EATL Project will be remembered as one of the pinnacle T&D Projects in Alberta. |
500kV Substation Project in Central Alberta
Owner: | ATCO |
Location: | Red Water, AB |
Award: | N/A |
Start Date: | N/A |
General: | Siemens Canada Ltd. |
As of Dec. of 2014, the project is approximately 100% complete. |